The U.S. power sector is in a once-in-a-generation period of unprecedented demand growth, driven by artificial intelligence, data centers, electrification, and reliability upgrades. Data centers will account for 13% of annual U.S. electricity demand by 2028. Grid operators forecast load growth not seen in decades. Grid uncertainty during extreme weather events compounds the need for new, reliable power generation. So, it is no wonder that utilities and developers are racing to bring new generation capacity online. Fast.

Large power users seek large, on-demand and reliable energy sources to support their electric needs. As a result, gas-fired power generation is re-emerging as a stable energy supply bridge until renewable energy can meet demand. Currently, U.S. gas generation facilities generate 378 gigawatts of energy with 50% for data centers.

Permitting, grid congestion, and turbine shortages

The gap between the desire to build and the ability to build is wide and growing rapidly. Despite investment, the road to developing and delivering new gas generation projects has plenty of obstacles.

  • Complex, multi-jurisdictional permitting processes involve overlapping procedures, agencies, timelines, regulatory and environmental requirements, and stakeholder opposition is slowing development. This is especially true when gas generation projects are tied to data center development and widespread public opposition. A Gallup poll found 7 in 10 Americans oppose data centers in their community. Public opposition is driving extensive stakeholder engagement and is a prerequisite for developing new gas generation projects in many jurisdictions.
  • Long lead times in gas turbines. Only a few manufacturers produce gas turbines, and the market was in decline, as solar and wind projects dominated the development of new generating capacity. The reversal of fortune has caught manufacturers under-prepared, leading to massive backorders in the highly specialized gas turbine supply chain.

Slaying the permitting dragon 

Permitting is the most formidable challenge because it has the longest lead times, requires technical design details that may be unknown early in the permitting process, and the process is influenced by a wide range of stakeholders. Permitting is also where developers can regain control. Regulatory compliance historically took up little space on a project development Gantt Chart; but today, permitting requires management time, subcontractor coordination, schedule changes, and a proactive stakeholder attitude from the beginning.

U.S. permitting is fragmented with a myriad of local, state, county, and federal regulations. Project specifics (e.g., location, capacity, zoning, etc.) determine which agency has primacy, but local authorities have substantial impact on what will be built. Local authorities typically can’t stop utility scale gas-fired power plants, although they can slow them down. On-site gas-fired power plants to power data centers is another story.  The authority of local authorities to block data center projects, and on-site gas-fired power generation associated with them, is broad, although the appetite to do so differs from state to state. Hundreds of datacenter moratoriums, mostly at the county and city level, are now active. Therefore, political and community sensitivities play an outsize role in project success.

Stakeholder engagement is not optional 

Since January 2024, 46 data center projects, across 20 states failed due to local resistance. This is $170B of projects that did not get built and capital that did not get deployed.

Overcoming local opposition will help data center gas generation projects get permitted. It is hard to get around local vetoes, and few U.S. state offers identical options to override them. This opposition is a rapidly growing project risk for gas generation projects, and proactive stakeholder engagement is a crucial part of the permitting process.

Many gas-powered projects are simultaneously developed and co-located with a data center and a gas pipeline project. Simultaneously co-locating three major capital projects requires developers to coordinate multiple, interdependent permits with no one controlling the overall permitting process. So, in addition to engineering feasibility and project economics, permit feasibility can determine if a project moves forward. For more information, read on data center permitting and community engagement.

The price of air emissions 

In certain regions, developers may need emissions offsets for nitrogen oxides, volatile organic compounds, fine particulates, and sulfur oxides. When required, these offsets are often scarce and very expensive. Permitted emission levels are a moving target against recently permitted facilities and evolving emissions standards. Power plant developers in certain areas must invest in lowering pollutant emissions or buy carbon credit through cap-and-trade.  Even in areas without offset requirements, these projects face an increasingly well-educated public who ask hard questions about emission levels, controls, impacts predicted by air dispersion modeling and long-term health effects. Submitting comprehensive and complete applications and data to address these concerns is key.

How to mitigate risks 

Developers must simultaneously screen multiple locations for transmission access, fuel supply, engineering, environmental impact, permitting risk and local opposition. The price of an incomplete assessment is substantial: delays, redesigns, escalating costs, or cancellation; not to mention energized stakeholders who dive into data and look for weak points.

  • What is the single most important aspect of successful permitting?  

Set a proactive decision structure that aligns siting, permitting, engineering, and stakeholder strategies from day one. The question is not where you can build or where demand exists; it is where you can get a permit. The most attractive site on paper is not always the one that can be permitted.

  • What are the most important environmental considerations for site selection? 

This can be hyper-local, and there is no one solution that fits all. Understanding local challenges early on and responding is key. For example, what is the ambient air quality at the site? Does existing air quality meet regulatory standards? What are the cumulative emissions of your power plant, data center, pipeline along with nearby large existing emission sources? What are zoning and land-use requirements? Are offsets or credits needed?  Are there state environmental justice requirements?

  • And what social and political aspects should we assess?  

Proactively gauge state and local political and community sentiment as these sentiments color how regulators will view your project and issue permits. Strong reservations may affect approval. A proactive engagement strategy with regulators, politicians, and communities is paramount.

  • Should permit-ability influence project siting (e.g., local veto of data center projects)?  

Yes. State agencies can neutralize local opposition to gas generation projects or choose not to. Being at odds with the local community is not ideal for a long-term gas generation project in general. Most datacenter projects can be stopped at the local level, halting on-site gas generation projects with them. So proactive stakeholder engagement is always the best route.

Conclusion 

As timelines become compressed and competition for capacity intensifies, developers cannot afford to uncover permitting challenges late in development. They must take an integrated approach, bringing environmental, permitting, engineering, and stakeholders together early on in project planning. In this tough and competitive market, a comprehensive strategy is essential to reduce risk and to accelerate delivery.